Bid Proposal · Prepared for Ms. Whylyn Maglangit Paduganao

Proposed Two-Storey Residence
Brgy. Gasi, Laguindingan

Submitted by JMG CONSTRUCTION & GENERAL MERCHANDISE, operating under the JMG Design & Build brand — a design-build partner built for clients who want the work done properly the first time.

Location
Floor Area
Architect of Record
Proposal Date
Grand Total — VAT Inclusive (12%)
Exterior perspective render of the Paduganao residence, daytime — proposed two-storey home with steel-blue hip roof, white masonry walls and stone-clad entrance columns
Perspective View — Day
Exterior perspective render of the Paduganao residence, evening — covered porch and landscape lighting
Perspective View — Evening
Read the Proposal
Executive Summary

This proposal is JMG's complete plan for building your home in Gasi, Laguindingan — not just a price, but the sequence, the standards, and the accountability behind it.

We've gone through Architect Gorospe's full drawing set — architectural, structural, plumbing and the outline specification — and priced the project the way we intend to build it: division by division, material by material, with nothing folded into a lump sum you can't verify.

One item in the drawings needed a decision before it could be priced fairly — the interior wood partition. Rather than guess and risk a change order later, we flagged it for your and the Architect's confirmation up front. You'll find it in Assumptions & Clarifications, not buried in fine print.

What follows is the full scope, the itemized cost build-up, a proposed construction schedule, and the payment structure we'd like to work under. We're ready to move as soon as you are.

Project
Client
Location
Ground Floor Area
Second Floor Area
Total Floor Area
Architect of Record
Master Plumber
Proposed Duration
ContractorJMG Construction & General Merchandise

Scope of Works

Fourteen divisions, priced to the drawings

Every division below traces directly to Architect Gorospe's plans and outline specification — structural, architectural, electrical and plumbing. Tap a division to see what's carried inside it.

What sits outside this bid: cabinetry — kitchen cabinets (melamine board, Hafele hardware, quartz counters) and bedroom/hallway closets — is priced separately on request; the interior wood partition is held pending confirmation with the Architect rather than estimated. Full detail under Assumptions & Clarifications.

Cost Summary

The full build-up, not just a bottom line

Direct costs by division, then overhead, contingency and profit shown separately — so you can see exactly what you're paying for and why. VAT is stated on its own line at every total.

Direct Cost
Sum of work divisions
OCM & Profit
Overhead 10% · Contingency 5% · Misc. 5% · Profit 12%
Total Construction Cost
VAT-exclusive
Grand Total
VAT-inclusive (12%)
Checking reconciliation…

Cost Distribution by Division

Direct cost only, before overhead/contingency/profit and VAT.
OSM = Owner-Supplied Material — fixture priced for labor/installation only; the unit itself is sourced and paid for by the Owner.
No line items match your search.
Grand Total

Construction Schedule

A proposed 26-week build, phase by phase

This is JMG's proposed contract duration for this scope — sequenced so structural, envelope, and MEP work don't collide, and cross-referenced to the payment schedule below. We'll confirm this with you before it's written into the contract.

Total duration: from mobilization to turnover.

Payment Schedule

Billing tied to completed work, not the calendar

Each progress billing is released against a specific, inspectable milestone from the schedule above — never a flat monthly draw. That's how both sides always know exactly where the money and the work stand.

Architect CertificationJMG submits each billing for the Architect's inspection and certification within calendar days of reaching the milestone.
Release TurnaroundOwner releases payment within calendar days of certification — kept current, this is what keeps the schedule above realistic.

Quality & Safety

The standards we build to, whether or not anyone's watching

Drawn from the project's own outline specification — this is what "built properly" means in practice on this job.

ACI-Compliant Concrete

Class A (1:2:4) for finish floors, slabs, beams & columns; Class B (1:2:3) for footings — 3,000 psi at 28 days, moist-cured a minimum of 7 consecutive days.

Brand-New Materials, Every Time

All materials brand new and of approved type and quality — no substitutions without our sign-off and yours, on record.

Code Compliance Across Trades

Plumbing to the National Plumbing Code, electrical to the Philippine Electrical Code, and every fire-rated assembly to the Fire Code of the Philippines with Resist-A-Flame treated wood framing.

Inspected Before It's Covered

Reinforcement, embedded items and rough-ins are inspected and approved before concrete is poured or a wall is closed up — not caught after the fact.

Three-Coat Finish Standard

Painting work is three-coat (primer, intermediate, finish) as standard, with Davies/Boysen-class materials selected and approved before any wall gets rolled.

Testing & Turnover, Not Just Handover

Preliminaries carry a dedicated testing-and-turnover line — MEP systems are commissioned and walked through with you before the keys change hands.


Our Team

One accountable point of contact, start to finish

Backed by a dedicated site engineer and office engineer working in constant sync — closing the gap between office planning and jobsite execution that slows down most builds.


Selected Work

Representative projects across JMG's design-build practice

A sample of recent and ongoing engagements — residential, retail, and commercial — showing the range JMG builds across, not a testimonial list.


Assumptions, Clarifications & Terms

What we confirmed before we priced this

A rigorous estimate names what it doesn't yet know, instead of quietly guessing. Here's everything we flagged while building this bid.

Excluded from this bid

    Basis of PricingPriced against the full architectural, structural and plumbing drawing set and outline specification dated 07-06-2026 (Sheet nos. A1–A4, S1–S3, P1–P2). Any revision to these drawings after contract signing is priced as a variation.
    Fixture SelectionBathroom and kitchen fixture allowances are priced and included; final brand/model selection stays with you, with JMG procuring and installing to your approved selection.
    VAT TreatmentAll division and summary figures above are VAT-exclusive; 12% VAT is added once, at the Grand Total, and shown on its own line everywhere the Grand Total appears.
    Site ReferenceWater supply connects to the Laguindingan Water District main per the plumbing plan; septic disposal is a two-chamber leaching-well system sized to the fixture count (42 WSFU) on Sheet P2.
    Next Step

    Let's build this the right way

    JMG CONSTRUCTION & GENERAL MERCHANDISE, operating under the JMG Design & Build brand, is a premium construction and design-build company focused on delivering high-quality, well-managed, and stress-free projects. Clients choose us when they want the work done properly the first time — this proposal is how we intend to earn that on your home in Gasi.

    Contractor of Record
    JMG Construction & General Merchandise
    operating as JMG Design & Build
    Contact
    Engr. Jasper M. Gementiza
    +63 917 105 6435
    engr@jaspergementiza.com
    Office
    Cambridge Subdivision, Harvard St.
    Block 7 Lot 32, Cagayan de Oro City 9000
    Licenses & Registration
    Prepared for Ms. Whylyn Maglangit Paduganao — Brgy. Gasi, Laguindingan, Misamis Oriental. This proposal is valid for 30 days from the date above and is subject to the terms stated herein.