JMG Design & Build recently completed the full design-build package for Happi Brew Main, a two-storey coffee shop construction project in Marawi City, Lanao del Sur. Commissioned by Amil Alonto and RJ Alonto, this project covers everything from architectural concept design to structural, electrical, plumbing, mechanical, and electronic/security working drawings — delivered as a complete, construction-ready document set under two proposal options.

About the Project

Happi Brew Main is designed as a modern two-storey commercial café building in Marawi City — an establishment built not just to serve great coffee, but to stand as a statement of quality in the local commercial landscape. The project was handled end-to-end by JMG Design & Build, ensuring that every drawing, every specification, and every cost estimate reflects the standard of work the client deserves.
The design takes full advantage of a two-storey layout: an open, welcoming ground-floor dining area with floor-to-ceiling glazing, a second-floor indoor dining space for a more intimate experience, and a signature alfresco terrace overlooking the surroundings. The architectural language is clean, contemporary, and built to age well.

Project Options Overview

Happi Brew Main
Two Engagement Options

Proposed Two-Storey Coffee Shop Building — Marawi City, Lanao del Sur

Amil Alonto & RJ Alonto
Happi Brew Main — Marawi City
JMG-OPT-2026-MRW-001
August 17, 2026
PHP 3,981,633.48
PHP 1,950,000.00
Section 01
How to Use This Document

JMG Design & Build has prepared two distinct engagement options for the Happi Brew Main project. Both options are based on the same approved architectural and structural design, the same DPWH 2024 unit rates, and the same above-average labor standards — the difference lies in who procures and supplies the materials.

Option A (Full Design & Build) — JMG handles everything: materials, labor, equipment, logistics, and project management. You get a single point of accountability, one contract, and a guaranteed turnkey outcome. This is our recommended path for most clients.

Option B (Manpower & PM Services Only) — JMG provides the workforce, supervision, and project management. You, the Owner, procure and supply all construction materials. This option works best when you have an established supplier network or require direct control over material specifications.

Review both options using the comparison table and decision guide below. Once you have decided, we will proceed with the corresponding full contract, schedule, and kick-off plan.

Section 02
Option Summaries
Option A

Full Design & Build

JMG supplies all — materials, labor, equipment, logistics & PM

₱3,981,633.48Lump-Sum | No VAT
  • All structural & finishing materials
  • Full skilled labor force
  • Equipment & tools
  • CDO-to-Marawi logistics
  • Project Engineer & Foreman
  • Quality control & documentation
  • Electrical, plumbing, MEP works
  • Turnkey handover with punchlist
  • Owner supplies: Approvals & NTP only
Recommended · Turnkey · Single Contract
Option B

Manpower & PM Only

JMG provides labor & management — Owner supplies materials

₱1,950,000.00Lump-Sum | No VAT
  • Full skilled labor force
  • Project Engineer & Foreman
  • Worker transport & accommodation
  • Site supervision & coordination
  • Quality control & documentation
  • 5-phase deployment plan
  • Owner supplies: All materials
  • Owner supplies: Equipment & tools
  • Owner arranges: Material logistics
Flexible · Labor-Only · Dual Contracts
Section 03
Pricing at a Glance
Option A
Full Design & Build Contract
₱3,981,633.48
No VAT · Lump-Sum · All-Inclusive
Direct Construction Cost₱3,263,633
OCM (12%)₱391,636
Contractor’s Profit (10%)₱326,363
Grand Total₱3,981,633.48
Option B
Manpower & PM Services Only
₱1,950,000.00
No VAT · Lump-Sum · Labor & Management
Direct Labor Cost₱1,598,400
OCM (12%)₱191,808
Contractor’s Profit (10%)₱159,840
Total Service Fee₱1,950,000.00

* Under Option B, the Owner’s total investment will include ₱1,950,000 (labor) plus the cost of all materials, equipment, and logistics procured separately — estimated at ₱2,031,633.48 based on BOQ v4, bringing the total project cost to approximately ₱3,981,633.48.

Section 04
Detailed Comparison
CategoryOption A — Full D&BOption B — Manpower Only
Contract & Pricing
Contract Value (No VAT)₱3,981,633.48₱1,950,000.00
Contract TypeLump-Sum Design-BuildLump-Sum Services Agreement
No. of Contracts Required1 Contract1 Services Contract (Owner handles materials separately)
Payment Structure5-tranche milestone billing5-tranche milestone billing
Mobilization Payment20% — ₱796,32720% — ₱390,000
Scope of Work
Structural Works (Concrete, Rebar, Formwork)✔ JMG supplies & installsLabor provided; Owner supplies materials
Masonry & Plastering✔ JMG supplies & installsLabor provided; Owner supplies CHB, cement
Roofing System✔ JMG supplies & installsLabor provided; Owner supplies roofing materials
Architectural Finishes (Tile, Paint, Doors)✔ JMG supplies & installsLabor provided; Owner supplies all finishes
Electrical Works (PEC-Compliant)✔ JMG supplies & installsLabor provided; Owner supplies panels, wires
Plumbing Works (National Plumbing Code)✔ JMG supplies & installsLabor provided; Owner supplies fixtures, pipes
CDO-to-Marawi Material Logistics✔ JMG manages all deliveriesOwner arranges
Equipment & Construction Tools✔ JMG providesOwner provides / rents
Management & Quality
Project Engineer (5 months)✔ Included✔ Included
Site Foreman✔ Included✔ Included
Quality Control & Inspection✔ Included✔ Included
Progress Reports (Monthly)✔ Included✔ Included
As-Built Documentation✔ Included✔ Included
Worker Accommodation (Marawi)✔ JMG arranges✔ JMG arranges
Risk & Accountability
Material Price Risk✔ JMG absorbs — fixed priceOwner bears — market price at time of purchase
Material Quality Risk✔ JMG controls & guaranteesOwner controls — JMG inspects on delivery
Supply Chain Coordination✔ Fully managed by JMGOwner coordinates with suppliers
Single Point of Accountability✔ Yes — JMG solely responsibleShared — JMG (labor) + Owner (materials)
Defect Liability Period1 Year (workmanship + materials)1 Year (workmanship only)
Timeline
Proposed Start DateSeptember 1, 2026September 1, 2026
Target CompletionJanuary 30, 2027 (22 weeks)January 16, 2027 (20 weeks)
Mobilization Lead Time7–10 days after NTP + 20% DP7–10 days after NTP + 20% DP
Section 05
Which Option Is Right for You?

Use this guide to choose the engagement model that best fits your situation, capacity, and priorities.

Choose Option A — Full Design & Build

If any of these describe your situation:
  • You want one contract, one call, one point of responsibility
  • You prefer a fixed price with no material cost surprises
  • You do not have time to manage suppliers and deliveries
  • You are not based in Marawi or CDO full-time
  • You want maximum JMG accountability over quality
  • You are building for business operation and need to open on time
  • You want the simplest, most professionally managed process

Choose Option B — Manpower & PM Only

If any of these describe your situation:
  • You already have trusted supplier relationships in CDO or Marawi
  • You can actively manage material procurement and deliveries
  • You want direct control over material brands and specifications
  • You are based in the area and can monitor supply chain closely
  • You have cash flow structured for separate labor & material payments
  • You want to spread procurement across multiple suppliers for cost control

JMG’s Professional Recommendation: For most clients, Option A delivers the better outcome. You eliminate coordination risk, material price exposure, and supply chain delays — all of which are significant factors in a remote-area project like Marawi. Our fixed-price approach means you know the final number before work begins. We stand behind the full project, not just the labor component.

Section 06
Document Set per Option

A complete document package is prepared for each option. Once you confirm your preferred engagement model, we can proceed to signing and mobilization.

📋
Project Proposal
Option A Option B
📊
Bill of Quantities
Option A Option B
📝
Construction Contract
Option A Option B
📅
Project Schedule
Option A Option B
Section 07
Next Steps
1

Select Your Option

Review both options and confirm which engagement model best fits your project goals and capacity. A simple email or call confirms your choice.

2

Sign the Contract

We finalize and execute the corresponding construction contract. Contract signing activates the project timeline and payment schedule.

3

Mobilize & Build

Upon receipt of the 20% mobilization payment and NTP, JMG deploys the team within 7–10 days. Construction begins on schedule.

Option A — Full Design & Build
Project Proposal

Happi Brew Main
Full Design & Build

Proposed Two-Storey Coffee Shop Building — Marawi City, Lanao del Sur

Amil Alonto & RJ Alonto
Marawi City, Lanao del Sur
JMG-PPA-2026-MRW-001
JMG-2026-MRW-001-R3
August 17, 2026
September 17, 2026
Lump-Sum Design-Build
No VAT
Option A — Full Design & Build
₱3,981,633.48
Lump-Sum, No VAT
All materials + labor + logistics
Section 01
Executive Summary

JMG Design & Build is pleased to present this Full Design & Build Proposal for the Proposed Two-Storey Coffee Shop Building — Happi Brew Main — located in Marawi City, Lanao del Sur. This engagement model represents our most comprehensive service offering: JMG assumes full responsibility for all materials, labor, equipment, logistics, and project management from mobilization to turnkey handover.

Under Option A, you make one decision — to build with JMG — and we handle the rest. You receive a fixed lump-sum price of PHP 3,981,633.48 (No VAT), a defined completion date, and a single point of accountability throughout the entire project lifecycle.

This proposal is based on the approved architectural and structural plans for a 10.90m × 6.00m two-storey reinforced concrete building with a Gross Floor Area of 130.80 square meters. All unit rates follow the DPWH 2024 Unit Price Guide, with Marawi remote-area premiums absorbed into all-in rates. No VAT is applied per project agreement.

Section 02
Why JMG Design & Build

JMG Construction & General Merchandise, operating under the JMG Design & Build brand, is a premium construction and design-build company focused on delivering high-quality, well-managed, and stress-free projects. Our clients choose us when they want the work done properly the first time.

Organized Project Management

Licensed Project Engineer on-site throughout construction. Structured progress reporting, milestone tracking, and documentation from day one.

Quality Workmanship

Above-average labor rates attract experienced craftsmen. All work follows NSCP, PEC, and National Plumbing Code standards. Defects addressed immediately.

Remote-Area Experience

We understand Marawi’s logistics, local conditions, and supply chain realities. Sourcing, transport, and accommodation are pre-planned, not improvised.

DPWH-Standard Pricing

All unit rates are based on DPWH 2024 benchmarks. You are paying for quality and process — not inflated margins disguised as expertise.

Section 03
Project Understanding

Happi Brew Main is a proposed two-storey reinforced concrete commercial building designed for coffee shop operations on the ground floor with auxiliary spaces on the second floor. The building is located in Marawi City, Lanao del Sur — a remote-area site approximately 140 km from Cagayan de Oro City (CDO), which serves as the primary sourcing and mobilization hub.

ParameterDetails
Building Footprint10.90m × 6.00m = 65.40 sqm per floor
Gross Floor Area (GFA)130.80 sqm (2 floors)
Building TypeTwo-Storey Reinforced Concrete (RC) Frame
Primary Structural SystemRC Columns (C1: 250×400mm, 6 pcs/floor) + RC Beams (B1, ~42 lm/floor)
FoundationReinforced concrete footings with embankment fill (175 cu.m)
Wall SystemCHB masonry — exterior net 168 sqm, interior 70 sqm
Plastering Area476 sqm (interior + exterior)
Project LocationMarawi City, Lanao del Sur (Remote Area Classification)
Distance from CDO (Supply Hub)~140 km, ~3.5 hours travel
Applicable CodesNSCP 2015, PEC 2017, National Plumbing Code, DPWH 2024
Section 04
Full Scope of Work — Option A

Under Option A, JMG Design & Build assumes full responsibility for all of the following work packages. All materials are sourced, delivered, and installed by JMG. All labor is recruited, supervised, and managed by JMG.

01 — Site Preparation & Earthworks

Site clearing, grubbing, excavation, compaction, embankment fill (175 cu.m loose), and rough grading to finished subgrade elevation.

02 — Concrete Works

All footings, grade beams, columns, slabs, and beams per structural plans. Concrete mix design, batch plant coordination, pour schedules, and curing.

03 — Formwork & Scaffolding

Full formwork system for all RC elements — fabrication, erection, stripping, and reuse planning. Perimeter scaffolding for safe access.

04 — Rebar Works

Structural steel reinforcement — bar cutting, bending, tying, and placement per NSCP 2015. Bar schedule and BBS prepared before cutting.

05 — Masonry & Plastering

CHB laying for exterior (168 sqm) and interior (70 sqm) walls, plus full-building plaster application (476 sqm). Cement-sand mortar with proper curing.

06 — Roofing System

Structural steel purlins, roof framing, long-span metal deck or corrugated roof sheets, gutters, downspouts, and ridge caps. Weathertight installation.

07 — Architectural Finishes

Tile works (floor and wall), doors and windows with hardware, ceiling framing and board, interior and exterior painting — all per approved finishes schedule.

08 — Electrical Works

PEC 2017-compliant complete electrical installation: distribution panel, branch circuits, conduit roughing-in, wiring, outlets, switches, lighting fixtures, and grounding system.

09 — Plumbing Works

National Plumbing Code-compliant complete installation: water supply lines, drainage system, comfort rooms, sinks, floor drains, water meter connection, and septic tank.

10 — Logistics & Material Delivery

All CDO-to-Marawi freight for bulk materials via 10-ton closed van/wing van. Multiple delivery runs coordinated with construction phases to minimize idle time.

11 — Project Management

Licensed Project Engineer (5 months), Site Foreman, monthly progress reports, quality inspections, daily site logs, and complete as-built documentation at turnover.

12 — Turnkey Handover

Final punchlist, defect correction, cleaning, commissioning of electrical and plumbing systems, and formal turnover with as-built drawings and warranties.

Items not included: land cost, permits and fees (Owner’s account), furniture and equipment (FF&E), utility connection fees, and any items specifically excluded in the agreed scope matrix.

Section 05
Bill of Quantities — Summary

The following table summarizes the major cost components per BOQ Reference JMG-2026-MRW-001-R3. The complete itemized BOQ with unit prices and quantities is available as a companion Excel document.

#Work PackageAmount (PHP)
A. Direct Construction Cost
ISite Preparation & Earthworks125,400.00
IIConcrete Works — Foundation, Columns, Beams, Slabs842,680.00
IIIFormwork & Scaffolding198,500.00
IVRebar / Structural Steel Reinforcement486,250.00
VMasonry Works (CHB) — Exterior & Interior Walls204,960.00
VIPlastering Works (476 sqm, both floors)133,280.00
VIIRoofing System (Structure, Decking, Gutters)286,400.00
VIIIArchitectural Finishes (Tile, Paint, Doors, Windows, Ceiling)418,663.67
IXElectrical Works — Complete Installation (PEC 2017)156,000.00
XPlumbing Works — Complete Installation (National Plumbing Code)142,500.00
XIMiscellaneous & Provisional Items269,000.00
Subtotal — Direct Construction Cost3,263,633.67
B. Markups
Overhead, Contingencies & Miscellaneous (OCM) — 12%391,636.04
Contractor’s Profit — 10%326,363.77
GRAND TOTAL — OPTION A (No VAT)₱3,981,633.48

* Detailed itemized BOQ (JMG-2026-MRW-001-R3) available as companion Excel file. All prices are in Philippine Peso. No VAT applied per project agreement.

Section 06
Contract Price & Payment Schedule
₱3,263,634
₱391,636
₱326,364
Lump-Sum · No VAT · All-Inclusive
₱3,981,633.48

Milestone Payment Schedule

#Milestone / Trigger%Amount (PHP)
1Mobilization — Upon contract signing + Notice to Proceed20%796,326.70
2Foundation Complete — Upon completion of all footings, grade beams, and ground floor slab25%995,408.37
3Structural Frame Complete — Upon completion of all columns, beams, and second floor slab25%995,408.37
4Enclosed & MEP Roughing-In — Roofing, masonry, doors, windows, electrical & plumbing roughing-in complete20%796,326.70
5Turnover — Final inspection, punchlist cleared, as-built documents delivered10%398,163.34
TOTAL CONTRACT PRICE100%₱3,981,633.48

Payment should be released within five (5) banking days of milestone completion and written certification by the Project Engineer. Payment delays beyond 15 days may affect the project schedule.

Section 07
Project Team

The following team will be deployed from Day 1. Key personnel are committed exclusively to the Happi Brew Main project for the duration of construction.

PositionDurationRate BasisResponsibilities
Project Engineer (Licensed)5 months₱1,500/dayOverall project management, quality control, owner liaison, documentation, billing certification
Site Foreman5 months₱1,200/dayDaily site supervision, crew coordination, materials management, safety enforcement
Master Mason (2 pcs)As required₱1,000/dayMasonry, plastering, concrete finishing, tile setting oversight
Carpenter / Formwork Specialist (2 pcs)As required₱1,000/dayFormwork fabrication, erection, stripping; door/window installation; ceiling works
Rebar Worker / Steel Man (2 pcs)As required₱1,000/dayBar cutting, bending, tying, placement per BBS; column and beam rebar assembly
Roofing Installer (2 pcs)As required₱1,000/dayStructural steel fabrication, purlin setting, roofing sheet installation, gutter and flashings
Licensed ElectricianAs required₱1,100/dayPEC 2017-compliant rough-in, panel installation, wiring, fixtures, testing
Licensed PlumberAs required₱1,100/dayWater supply, drainage, rough-in, fixtures installation, pressure testing
Tile Setter (2 pcs)As required₱950/dayFloor and wall tile setting, grouting, waterproofing integration
Painter (2 pcs)As required₱950/daySurface preparation, primer, paint application — interior and exterior
General Laborers (4 pcs)110 days₱650/dayConcrete works support, material handling, site maintenance, general assistance

All rates are all-in: inclusive of SSS, PhilHealth, HDMF, and Marawi remote-area premium (+12% absorbed into daily rates). Rates comply with and exceed DOLE BARMM minimum wage standards.

Section 08
Project Schedule Overview

The project is programmed for a 22-week construction period commencing September 1, 2026 with a target completion date of January 30, 2027.

PhaseActivitiesWeeks
Phase 1
Mobilization & Site Prep
Site setup, permits coordination, earthworks, embankment fill, excavationWeeks 1–3
Phase 2
Foundation & Ground Floor
Footing excavation & pour, grade beams, columns (ground floor), ground floor slabWeeks 3–8
Phase 3
Second Floor Structure
Second floor columns, beams, slab; structural steel works; roofing frameWeeks 8–14
Phase 4
Enclosure & MEP Rough-In
Masonry all floors, roofing installation, doors & windows, electrical & plumbing rough-in, plasteringWeeks 13–18
Phase 5
Finishes & Turnover
Tile, ceiling, painting, fixtures, MEP testing, final inspection, punchlist, as-built documentationWeeks 18–22

A detailed 22-week Gantt chart (document ref: JMG-SCH-OPA-2026-MRW-001) is provided as a companion document. Schedule subject to Owner providing NTP and 20% mobilization payment on or before August 31, 2026.

Section 09
Terms & Conditions
1

Contract Type & Pricing Basis

This is a lump-sum Design-Build contract. The contract price of PHP 3,981,633.48 is fixed and all-inclusive for the defined scope of work. No VAT is applied per project agreement. No additional charges for materials, labor, or logistics within the agreed scope.

2

Scope Variations

Any Owner-initiated additions, deletions, or modifications to the agreed scope will be subject to a written Change Order and price adjustment. JMG will provide cost estimates within 5 business days of any variation request. Works do not proceed without Owner sign-off on the Change Order.

3

Owner’s Responsibilities

The Owner shall: (a) secure all building permits and government clearances prior to NTP; (b) provide clear, unobstructed site access; (c) release payments within 5 banking days of milestone certification; (d) provide written NTP before construction commencement.

4

Validity Period

This proposal is valid for thirty (30) calendar days from the date of issue. After September 17, 2026, prices are subject to revision based on material and labor market conditions. JMG reserves the right to re-price should material costs move by more than 5% from current benchmark rates.

5

Defect Liability & Warranty

JMG warrants all workmanship and supplied materials for one (1) year from the date of turnover. Any structural or material defects attributable to JMG will be corrected at no additional cost to the Owner. Defects caused by Owner misuse, unauthorized alterations, or force majeure are excluded.

6

Force Majeure

Neither party shall be in default for delays caused by events beyond reasonable control, including but not limited to natural disasters, civil unrest, government-mandated lockdowns, or declared state of calamity. Both parties will negotiate a reasonable schedule extension in good faith.

7

Payment Default

If the Owner fails to release payment within fifteen (15) calendar days of milestone certification, JMG may suspend construction without penalty until payment is received. Resulting delays due to payment suspension will extend the project completion date accordingly and are not attributable to JMG.

Section 10
Proposal Acceptance

By signing below, the Owner confirms acceptance of this Proposal

This constitutes the Owner’s intent to proceed with Option A — Full Design & Build at the contract price of PHP 3,981,633.48 (No VAT) under the terms and conditions outlined herein. A formal Construction Contract (JMG-CON-OPA-2026-MRW-001) will be executed as the binding legal instrument. This accepted proposal serves as a Letter of Intent until the contract is signed.

Amil Alonto & RJ Alonto
Owner — Happi Brew Main, Marawi City
Date: _______________________
JMG Design & Build
JMG Construction & General Merchandise
Authorized Representative
Date: _______________________
Proposal Ref: JMG-PPA-2026-MRW-001 | BOQ Ref: JMG-2026-MRW-001-R3 | Date Issued: August 17, 2026 | Valid Until: September 17, 2026
Option A — Full Design & Build
Construction Contract

Happi Brew Main
Design-Build Contract

Contract No. JMG-CON-OPA-2026-MRW-001

JMG-CON-OPA-2026-MRW-001
Lump-Sum Design-Build
Amil Alonto & RJ Alonto
JMG Construction & General Merchandise
Happi Brew Main — Two-Storey Coffee Shop
Marawi City, Lanao del Sur
PHP 3,981,633.48 (No VAT)
August 17, 2026
Option A — Full Design & Build Contract
₱3,981,633.48
Lump-Sum · No VAT
All Materials + Labor + Logistics

This Construction Contract (“Contract”) is entered into as of ________________, 2026, by and between the following parties:

The Owner
Amil Alonto & RJ Alonto
Owner — Happi Brew Main
Marawi City, Lanao del Sur
Philippines
(hereinafter referred to as the “Owner”)
AND
The Contractor
JMG Construction & General Merchandise
Operating as JMG Design & Build
Philippines

(hereinafter referred to as the “Contractor”)
Recitals
Background & Recitals

WHEREAS, the Owner intends to construct a Proposed Two-Storey Coffee Shop Building — Happi Brew Main — located in Marawi City, Lanao del Sur, Philippines (the “Project”);

WHEREAS, the Contractor is a duly organized construction enterprise engaged in building construction, design-build, and project management services in the Philippines;

WHEREAS, the Owner desires to engage the Contractor under a Full Design-Build arrangement, wherein the Contractor provides all labor, materials, equipment, and logistics required to complete the Project from mobilization to turnkey handover;

WHEREAS, the Contractor has prepared and submitted a detailed Bill of Quantities (BOQ Ref: JMG-2026-MRW-001-R3) and Project Proposal (Ref: JMG-PPA-2026-MRW-001), which the Owner has reviewed, approved, and accepted;

NOW THEREFORE, in consideration of the mutual covenants herein and for good and valuable consideration, the parties agree as follows:

Article I
Scope of Work
1.1
The Contractor agrees to furnish all labor, materials, equipment, tools, transportation, supervision, and related services necessary to complete the construction of the Proposed Two-Storey Coffee Shop Building — Happi Brew Main, in Marawi City, Lanao del Sur, in accordance with the approved plans, specifications, and the Bill of Quantities (Ref: JMG-2026-MRW-001-R3).
1.2
The full scope includes, but is not limited to: site preparation and earthworks; reinforced concrete foundations, columns, beams, and slabs; formwork and scaffolding; structural steel reinforcement; masonry and plastering; roofing system; architectural finishes (tile, paint, doors, windows, ceiling); complete electrical installation (PEC 2017-compliant); complete plumbing installation (National Plumbing Code-compliant); CDO-to-Marawi material logistics; and project management for the duration of construction.
1.3
The Contractor warrants that all materials supplied shall be of good quality, appropriate grade, and consistent with the specifications referenced in the approved BOQ. No substitution of specified materials shall be made without prior written consent from the Owner.
1.4
Items Excluded from Scope: land acquisition and titling costs; building permit fees and government processing charges; furniture, fixtures, and equipment (FF&E) beyond those listed in the BOQ; utility connection and meter installation fees; and any works specifically identified as Owner-supplied in the approved scope matrix.
Article II
Contract Price
Full Design & Build — Total Contract Price
Direct Construction Cost: ₱3,263,633.67
Overhead, Contingencies & Misc. (OCM 12%): ₱391,636.04
Contractor’s Profit (10%): ₱326,363.77
₱3,981,633.48
Philippine Peso · No VAT
Lump-Sum Fixed Price
2.1
The Owner agrees to pay the Contractor a total lump-sum price of Philippine Pesos Three Million Nine Hundred Eighty-One Thousand Six Hundred Thirty-Three and 48/100 (PHP 3,981,633.48) for the full completion of the defined scope of work. No Value Added Tax (VAT) is applied per the parties’ agreement.
2.2
This contract price is fixed and all-inclusive for the approved scope. It shall not be adjusted except through a written, mutually-signed Change Order as provided in Article VIII of this Contract.
2.3
The contract price is based on DPWH 2024 Unit Price Guide rates, above-average labor rates with Marawi remote-area premium (+12%) absorbed into all-in daily rates, and CDO-sourced material pricing as of the date of BOQ preparation.
Article III
Payment Schedule
3.1
Payment shall be released in five (5) tranches tied to construction milestones as follows:
TrancheMilestone Trigger%Amount (PHP)
1stMobilization — upon contract execution and written NTP20%796,326.70
2ndFoundation Complete — all footings, grade beams, ground floor slab poured and cured25%995,408.37
3rdStructural Frame Complete — all columns, beams, second floor slab, and roofing structure25%995,408.37
4thEnclosed & MEP Rough-In — roofing, masonry, doors, windows, electrical and plumbing rough-in done20%796,326.70
5thTurnover — final inspection complete, punchlist cleared, as-built documents submitted10%398,163.34
TOTAL CONTRACT PRICE100%₱3,981,633.48
3.2
Milestone completion shall be certified in writing by the Contractor’s Project Engineer. The Owner shall release payment within five (5) banking days of receiving the written milestone certification. Billing shall be accompanied by progress photographs and a brief status report.
3.3
If payment is delayed beyond fifteen (15) calendar days from the due date without written justification from the Owner, the Contractor reserves the right to suspend construction activities. Any resulting schedule delays due to payment suspension shall extend the project completion date accordingly and shall not be attributed to the Contractor.
3.4
All payments shall be made via bank transfer or manager’s check payable to JMG Construction & General Merchandise. Cash payments will be acknowledged through official receipts issued by the Contractor.
Article IV
Time of Completion
4.1
The Contractor shall commence construction on or before the date specified in the written Notice to Proceed (NTP) issued by the Owner, provided that the 20% mobilization payment (₱796,326.70) has been received by the Contractor. The Contractor shall mobilize within seven (7) to ten (10) calendar days of receiving both the NTP and mobilization payment.
4.2
The proposed NTP date is September 1, 2026. The target project completion date is January 30, 2027 — a construction period of approximately twenty-two (22) weeks, exclusive of force majeure and Owner-caused delays.
4.3
The project schedule is detailed in the companion Gantt chart (Ref: JMG-SCH-OPA-2026-MRW-001). Both parties acknowledge that the schedule may be adjusted by mutual written agreement without invalidating this Contract.
4.4
Time extensions shall be granted for: (a) Owner-directed scope changes; (b) payment delays beyond 15 days causing a work suspension; (c) force majeure events; (d) Owner failure to provide timely access, decisions, or approvals. Extensions shall be formalized through a written Time Extension Order signed by both parties.
Article V
Contractor’s Obligations
5.1
Workmanship Quality: The Contractor shall perform all work in a professional and workmanlike manner, in accordance with NSCP 2015, PEC 2017, the National Plumbing Code of the Philippines, and DPWH standard specifications.
5.2
Licensed Personnel: The Contractor shall assign a licensed Professional Engineer or Civil Engineer as Project Engineer, and a qualified Site Foreman, for the full duration of construction.
5.3
Progress Reporting: The Contractor shall submit a written monthly progress report by the 1st business day of each month, including: work accomplished, upcoming activities, issues encountered, and photographic documentation.
5.4
Site Safety: The Contractor is responsible for maintaining a safe working environment on site. All workers shall be provided with appropriate PPE. The Contractor shall comply with DOLE occupational safety standards for construction.
5.5
Material Control: The Contractor shall source and use only materials of specified quality. The Owner may inspect materials before and during installation. Non-conforming materials shall be removed and replaced at no additional cost.
5.6
As-Built Documentation: Upon turnover, the Contractor shall provide complete as-built drawings (architectural, structural, electrical, plumbing), operating manuals for installed systems, and warranty certificates for supplied materials and equipment.
Article VI
Owner’s Obligations
6.1
Permits & Clearances: The Owner is responsible for securing all required building permits, barangay clearances, and government approvals prior to the issuance of NTP. No NTP shall be issued until the building permit is presented to the Contractor.
6.2
Site Access: The Owner shall provide clear, legal, and unobstructed access to the project site at all times during normal working hours. Any access disputes or restrictions shall be resolved by the Owner promptly.
6.3
Timely Payments: The Owner shall release each payment tranche within five (5) banking days of receiving the written milestone certification. Delayed payments directly affect the project schedule.
6.4
Timely Decisions: The Owner shall respond to Contractor requests for decisions, approvals, or clarifications within five (5) business days. Delays in Owner decisions that affect the construction schedule shall be documented and may entitle the Contractor to a time extension.
Article VII
Defect Liability & Warranty
7.1
The Contractor warrants all workmanship and materials supplied under this Contract for a period of one (1) year from the date of formal turnover (the “Defect Liability Period”). Any defects in workmanship or supplied materials identified during this period shall be corrected by the Contractor at no additional cost to the Owner.
7.2
The warranty does not cover defects arising from: (a) Owner misuse or unauthorized modifications; (b) normal wear and tear; (c) force majeure or natural disasters; (d) acts of third parties not engaged by the Contractor.
7.3
The Owner shall notify the Contractor in writing of any warranty claim. The Contractor shall inspect and respond within five (5) business days. Confirmed warranty defects shall be remediated within a reasonable time as agreed by both parties.
Article VIII
Change Orders & Scope Variations
8.1
Any change to the scope of work — additions, deletions, or modifications — must be authorized through a written Change Order signed by both parties before work begins on the variation. No verbal or email-only authorizations are binding.
8.2
The Contractor shall provide a written cost estimate for any proposed change within five (5) business days of the Owner’s request. The estimate shall reference DPWH 2024 unit rates. Both parties shall negotiate in good faith before executing the Change Order.
8.3
Approved Change Orders shall specify: description of work, adjusted price (addition or deduction), and any schedule impact. The cumulative effect of all Change Orders shall be added to or deducted from the original contract price.
Article IX & X
Force Majeure & Dispute Resolution
Article IX — Force Majeure
9.1
Neither party shall be held in default or liable for delays or failures in performance caused by events beyond their reasonable control, including but not limited to: natural disasters (earthquake, flooding, typhoon), declared state of calamity or emergency, civil unrest, national or local government-mandated lockdowns, or acts of God.
9.2
The affected party shall provide written notice of the force majeure event within five (5) business days. Both parties shall negotiate in good faith a reasonable schedule extension and, if necessary, a price adjustment for any additional mobilization or standby costs incurred.
Article X — Dispute Resolution
10.1
The parties shall make every reasonable effort to resolve disputes amicably through direct negotiation within fifteen (15) calendar days of written notice of a dispute. If negotiation fails, the dispute may be referred to a mutually-agreed mediator or submitted to the appropriate court of jurisdiction in the Philippines.
10.2
This Contract shall be governed by and construed in accordance with the laws of the Republic of the Philippines. The parties consent to the exclusive jurisdiction of the appropriate Philippine courts for any dispute arising from this Contract.
Execution
Contract Execution

IN WITNESS WHEREOF, the parties have executed this Construction Contract as of the date first written above. Each party acknowledges having read and understood the full terms and conditions herein.

Amil Alonto & RJ Alonto
Owner — Happi Brew Main
Marawi City, Lanao del Sur
Date:
JMG Design & Build
JMG Construction & General Merchandise
Authorized Representative
Date:

Signed in the Presence of the Following Witnesses

Printed Name & Signature
Printed Name & Signature
Contract No. JMG-CON-OPA-2026-MRW-001 | Proposal Ref: JMG-PPA-2026-MRW-001 | BOQ Ref: JMG-2026-MRW-001-R3
Option A — Full Design & Build | Contract Price: ₱3,981,633.48 (No VAT) | August 17, 2026
Option A — Full Design & Build
Project Schedule

Happi Brew Main — Construction Schedule

22-Week Program of Works | September 2026 – January 2027

JMG-SCH-OPA-2026-MRW-001
September 1, 2026
January 30, 2027
22 Weeks
Amil Alonto & RJ Alonto
Happi Brew Main, Marawi City
₱3,981,633.48
JMG-CON-OPA-2026-MRW-001
Option A — Full Design & Build
22 Weeks · Sept 1, 2026 → Jan 30, 2027
₱3,981,633.48 · 5 Payment Milestones
Legend:
Phase 1 — Mobilization
Phase 2 — Foundation & GF
Phase 3 — 2F Structure
Phase 4 — Enclosure & MEP
Phase 5 — Finishes
 Payment Milestone
ActivitySeptember 2026October 2026November 2026December 2026January 2027
Week →W1W2W3W4W5W6W7W8W9W10W11W12W13W14W15W16W17W18W19W20W21W22
Date Range →1-58-1215-1922-2629-36-1013-1720-2427-313-710-1417-2124-281-58-1215-1922-2629-25-912-1619-2326-30
PHASE 1 — MOBILIZATION & SITE PREPARATION (Weeks 1–3)
1.1Mobilization, Site Setup & Temporary Facilities
1.2Permits Coordination & Submission
1.3Site Clearing, Grubbing & Demolition (if any)
1.4Earthworks — Excavation, Embankment Fill (175 cu.m), Compaction
💰 PAYMENT 1 — 20% Mobilization (₱796,327)
PHASE 2 — FOUNDATION & GROUND FLOOR STRUCTURE (Weeks 3–8)
2.1Footing Excavation, Layout & Rebar Assembly
2.2Footing Concrete Pouring & Curing
2.3Grade Beams — Rebar, Formwork & Concrete
2.4Ground Floor Columns — Rebar, Formwork & Pour (6 pcs)
2.5Ground Floor Beams, Slab Formwork & Rebar
2.6Ground Floor Slab & Beam Concrete Pour
💰 PAYMENT 2 — 25% Foundation Complete (₱995,408)
PHASE 3 — SECOND FLOOR STRUCTURE & ROOFING (Weeks 8–14)
3.12nd Floor Columns — Rebar, Formwork & Pour (6 pcs)
3.22nd Floor Beams — Rebar, Formwork
3.32nd Floor Slab — Formwork, Rebar & Concrete Pour
3.4Roof Framing — Structural Steel, Purlins & Trusses
💰 PAYMENT 3 — 25% Structural Frame Complete (₱995,408)
PHASE 4 — ENCLOSURE, MASONRY & MEP ROUGH-IN (Weeks 13–18)
4.1Roofing Sheet Installation, Gutters & Flashings
4.2CHB Masonry — Ground Floor Walls (Exterior 84 sqm + Interior 35 sqm)
4.3CHB Masonry — 2nd Floor Walls (Exterior 84 sqm + Interior 35 sqm)
4.4Doors & Windows — Frame, Installation & Hardware
4.5Electrical Rough-In — Conduit, Boxes & Panel (PEC 2017)
4.6Plumbing Rough-In — Water Supply, Drain & Vent Lines
4.7Cement Plastering — All Walls Interior & Exterior (476 sqm)
💰 PAYMENT 4 — 20% Enclosed + MEP Rough-In (₱796,327)
PHASE 5 — FINISHES, MEP COMPLETION & TURNOVER (Weeks 18–22)
5.1Floor Tile Setting — Ground Floor & 2nd Floor
5.2Wall Tile Setting — CR, Kitchen, Wet Areas
5.3Ceiling Works — Framing & Board Installation
5.4Interior & Exterior Painting — Primer + Finish Coats
5.5Electrical — Wiring, Panel, Fixtures, Switches & Testing
5.6Plumbing — Fixtures, CR Works, Testing & Commissioning
5.7Final Inspection, Punchlist & Defect Corrections
5.8As-Built Documentation, Warranties & Formal Turnover
💰 PAYMENT 5 — 10% Turnover (₱398,163)
Project Summary
Phase Overview & Payment Schedule
Phase 1
Mobilization & Site Preparation
Weeks 1–3
Sep 1 – Sep 19, 2026
💰 20% — ₱796,327
Phase 2
Foundation & Ground Floor Structure
Weeks 3–10
Sep 15 – Oct 31, 2026
💰 25% — ₱995,408
Phase 3
Second Floor Structure & Roofing
Weeks 8–15
Oct 20 – Dec 5, 2026
💰 25% — ₱995,408
Phase 4
Enclosure, Masonry & MEP Rough-In
Weeks 13–18
Nov 24 – Jan 2, 2027
💰 20% — ₱796,327
Phase 5
Finishes, MEP Completion & Turnover
Weeks 18–22
Jan 5 – Jan 30, 2027
💰 10% — ₱398,163
Total Contract Duration
22 Weeks · September 1, 2026 → January 30, 2027
Total Contract Price
₱3,981,633.48
No VAT | Lump-Sum | All-Inclusive
Option B — Manpower & PM Services Only
Project Proposal

Happi Brew Main
Manpower & PM Services

Proposed Two-Storey Coffee Shop Building — Marawi City, Lanao del Sur

Amil Alonto & RJ Alonto
Marawi City, Lanao del Sur
JMG-PPB-2026-MRW-001
JMG-MPS-2026-MRW-001-R1
August 17, 2026
September 17, 2026
Lump-Sum Manpower Services
No VAT
Option B — Manpower & PM Services Only
₱1,950,000.00
Lump-Sum, No VAT
Labor + Management Only
ℹ️

Important — Owner Supplies All Materials Under This Option

Under Option B, JMG provides the complete workforce, project management, and logistics for workers. The Owner is responsible for procuring, funding, and delivering all construction materials, equipment, and tools to site. A separate BOQ (JMG-2026-MRW-001-R3) is provided as a material procurement guide for the Owner’s reference.

Section 01
Executive Summary

JMG Design & Build is pleased to present this Manpower & Project Management Services Proposal for the Proposed Two-Storey Coffee Shop Building — Happi Brew Main — in Marawi City, Lanao del Sur. Under Option B, JMG provides a complete, professional workforce and management team while the Owner retains full control of material procurement.

Under Option B, JMG’s role is to deploy the right team, manage the process, and build correctly — using the materials you supply. The total service fee is PHP 1,950,000.00 (No VAT) — a lump-sum, fixed price for all labor, supervision, worker logistics, and project management from mobilization to handover.

This proposal is built on the same approved architectural and structural plans and the same DPWH 2024 labor rate standards as Option A. The only difference is that you, the Owner, control material sourcing. JMG’s labor rates include the Marawi remote-area premium (+12%) absorbed into all daily rates — workers are paid above-average, ensuring you attract and retain experienced craftsmen on your project.

Section 02
Clear Division of Responsibilities

Under Option B, responsibilities are clearly divided between JMG and the Owner. Understanding this split before signing protects both parties and keeps the project on schedule.

🏗 JMG Provides

  • Licensed Project Engineer (5 months full-time)
  • Qualified Site Foreman
  • Master Masons, Carpenters, Rebar Workers
  • Licensed Electrician & Licensed Plumber
  • Roofing Installers, Tile Setters, Painters
  • General Laborers (4 pcs × 110 days)
  • Worker transport (CDO–Marawi, 20 trips)
  • Worker accommodation in Marawi (5 months)
  • Site supervision & daily work coordination
  • Quality control & inspection
  • Monthly progress reports
  • As-built documentation at turnover

📦 Owner Provides

  • All structural materials (cement, rebar, aggregate)
  • All CHB, mortar, plastering materials
  • All roofing materials (sheets, purlins, gutters)
  • All architectural finishes (tile, paint, doors)
  • All electrical materials (wire, panels, conduit)
  • All plumbing materials (pipes, fixtures, fittings)
  • Construction equipment & power tools on site
  • Material delivery from suppliers to site
  • Water and temporary power supply
  • Building permit and government fees
  • Site access and security
  • Scaffolding & formwork materials (if not in BOQ labor)

JMG will inspect all materials upon delivery and may reject substandard materials that do not meet the project specifications. Delivery delays caused by material shortages on the Owner’s side will extend the project schedule accordingly.

Section 03
Scope of Labor Services

JMG’s labor team will execute all of the following activities using materials supplied by the Owner.

Earthworks & Site Prep

Site clearing, excavation, compaction, embankment fill (175 cu.m), and rough grading per structural drawings.

Concrete Works

Form, reinforce, pour, and cure all footings, grade beams, columns, beams, and slabs on both floors.

Formwork & Scaffolding

Fabrication, erection, and stripping of all formwork for RC elements. Scaffolding erection and dismantling.

Rebar / Structural Steel

Bar cutting, bending, tying, and placement per bar schedule. Steel column installation and welding where required.

Masonry & Plastering

CHB laying (168 sqm exterior + 70 sqm interior) and full plastering (476 sqm) on both floors.

Roofing Installation

Structural steel purlin setting, roofing sheet installation, gutters, downspouts, and ridge caps.

Doors & Windows

Frame installation, door hanging, window setting, and hardware installation per schedule.

Tile Works

Floor and wall tile setting (with materials supplied by Owner). Waterproofing integration for wet areas.

Ceiling Works

Ceiling frame fabrication and board installation per approved ceiling plan.

Painting

Surface preparation, primer, and finish coat application — interior and exterior, all surfaces.

Electrical Installation

PEC 2017-compliant rough-in, wiring, panel installation, fixture mounting, and testing.

Plumbing Installation

Water supply and drainage rough-in, fixture installation, pressure testing per National Plumbing Code.

Section 04
Labor Rate Schedule

All daily rates below are all-in — inclusive of SSS, PhilHealth, HDMF, and the Marawi remote-area premium (+12%) absorbed directly into the rate. No separate premium line item is billed.

#PositionDaily RateDOLE BARMM Min.Premium vs. Min.
1Project Engineer (Licensed PH)₱1,500~₱600+150%
2Site Foreman₱1,200~₱550+118%
3Master Mason₱1,000₱500+100%
4Carpenter / Formwork Specialist₱1,000₱500+100%
5Rebar Worker / Steel Man₱1,000₱500+100%
6Roofing Installer₱1,000₱500+100%
7Licensed Electrician₱1,100₱500+120%
8Licensed Plumber₱1,100₱500+120%
9Tile Setter₱950₱500+90%
10Painter₱950₱500+90%
11General Laborer₱650₱500+30%

DOLE BARMM minimum wage reference: Wage Order No. BARMM-02 (effective 2024). Above-average rates ensure we attract experienced, reliable workers — not the cheapest hands available. This directly protects the quality of your project.

Section 05
Detailed Cost Breakdown
Cost ComponentAmount (PHP)
A. Project Management Team
PEProject Engineer — ₱1,500/day × 22 days/mo × 5 months + benefits165,000.00
FMSite Foreman — ₱1,200/day × 22 days/mo × 5 months132,000.00
PM Team Subtotal297,000.00
B. Skilled Trades
MAMaster Masons (2 pcs) — ₱1,000/day × 90 days × 2180,000.00
CACarpenters (2 pcs) — ₱1,000/day × 80 days × 2160,000.00
RBRebar Workers (2 pcs) — ₱1,000/day × 60 days × 2120,000.00
RFRoofing Installers (2 pcs) — ₱1,000/day × 30 days × 260,000.00
ELLicensed Electrician — ₱1,100/day × 45 days49,500.00
PLLicensed Plumber — ₱1,100/day × 40 days44,000.00
TSTile Setters (2 pcs) — ₱950/day × 40 days × 276,000.00
PTPainters (2 pcs) — ₱950/day × 30 days × 257,000.00
Skilled Trades Subtotal746,500.00
C. General Labor
GLGeneral Laborers (4 pcs) — ₱650/day × 110 days × 4286,000.00
D. Logistics & Accommodation
TRWorker Transport CDO–Marawi (20 round trips × ₱3,500)70,000.00
ACWorker Accommodation in Marawi (5 months × ₱28,000)140,000.00
E. PM Services Fee
PMProject Management, Coordination & Documentation Fee76,500.00
Total Direct Service Cost1,616,000.00
F. Markups
Overhead, Contingencies & Miscellaneous (OCM) — 12%173,808.00
Contractor’s Profit — 10%160,192.00
TOTAL SERVICE FEE — OPTION B (No VAT)₱1,950,000.00
Section 06
Fee Summary & Payment Schedule
₱1,598,400
₱191,808
₱159,840
Lump-Sum · No VAT · Labor & Management Only
₱1,950,000.00

Milestone Payment Schedule

#Milestone / Trigger%Amount (PHP)
1Mobilization — Upon signing + NTP + site is ready for workers20%390,000.00
2Foundation Phase — All footings, grade beams, GF slab complete25%487,500.00
3Structural Frame — All columns, beams, 2F slab, roofing frame complete25%487,500.00
4Enclosed + MEP — Masonry, roofing, electrical & plumbing rough-in done20%390,000.00
5Turnover — All finishes complete, punchlist cleared, as-built submitted10%195,000.00
TOTAL SERVICE FEE100%₱1,950,000.00

Note: Milestone payment releases are contingent on JMG’s labor milestone only. If material supply delays affect progress, the milestone timeline adjusts accordingly — but payment for completed labor work is still due as certified.

Section 07
Key Terms & Conditions
1

Lump-Sum Labor Contract

This is a fixed lump-sum for all labor, supervision, worker logistics, and project management. No VAT is applied. The fee does not cover any materials, equipment, or tools.

2

Material Supply is Owner’s Responsibility

All construction materials must be procured, funded, and delivered to site by the Owner per the project schedule. JMG is not responsible for delays caused by material shortages or late deliveries. Such delays will extend the completion date and are not attributable to JMG.

3

Material Quality Inspection

JMG’s Project Engineer will inspect all materials upon delivery. Non-conforming materials will be flagged in writing. JMG reserves the right to refuse installation of materials that do not meet specified standards — doing so protects both parties from defects and liability.

4

Defect Liability — Workmanship Only

JMG’s one (1) year warranty under Option B covers workmanship only. Material defects are the responsibility of the material supplier or the Owner’s procurement choices. JMG will correct installation-related defects at no charge within the warranty period.

5

Validity & Scope Changes

This proposal is valid for 30 days from issuance. Any scope changes (additions or deletions in labor scope) require a written Change Order. Labor rate adjustments due to market escalation after 90 days from NTP may be subject to renegotiation.

Section 08
Proposal Acceptance

By signing below, the Owner confirms acceptance of this Proposal

This confirms intent to proceed with Option B — Manpower & PM Services Only at a total service fee of PHP 1,950,000.00 (No VAT). A formal Manpower & PM Services Contract (JMG-CON-OPB-2026-MRW-001) will be executed as the binding instrument.

Amil Alonto & RJ Alonto
Owner — Happi Brew Main, Marawi City
Date: _______________________
JMG Design & Build
JMG Construction & General Merchandise
Authorized Representative
Date: _______________________
Proposal Ref: JMG-PPB-2026-MRW-001 | MPS Ref: JMG-MPS-2026-MRW-001-R1 | BOQ Ref: JMG-2026-MRW-001-R3 | August 17, 2026
Option B — Manpower & PM Services Only
Manpower & PM Services Contract

Happi Brew Main
Labor & PM Contract

Contract No. JMG-CON-OPB-2026-MRW-001

JMG-CON-OPB-2026-MRW-001
Lump-Sum Manpower & PM Services
Amil Alonto & RJ Alonto
JMG Construction & General Merchandise
Happi Brew Main — Two-Storey Coffee Shop
Marawi City, Lanao del Sur
PHP 1,950,000.00 (No VAT)
August 17, 2026
Option B — Manpower & PM Services Only
₱1,950,000.00
Lump-Sum · No VAT
Labor + Management · Owner Supplies Materials

This Manpower & Project Management Services Contract (“Contract”) is entered into as of ________________, 2026, by and between the following parties:

The Client / Owner
Amil Alonto & RJ Alonto
Owner — Happi Brew Main
Marawi City, Lanao del Sur
Philippines
(hereinafter referred to as the “Owner”)
AND
The Service Provider
JMG Construction & General Merchandise
Operating as JMG Design & Build
Philippines

(hereinafter referred to as the “Contractor”)
Recitals
Background & Recitals

WHEREAS, the Owner intends to construct a Proposed Two-Storey Coffee Shop Building — Happi Brew Main — located in Marawi City, Lanao del Sur, Philippines (the “Project”);

WHEREAS, the Owner has elected to procure and supply all construction materials directly and desires to engage the Contractor solely for manpower, skilled labor, project management, and related logistics services;

WHEREAS, the Contractor has submitted a Manpower & PM Services Proposal (Ref: JMG-MPS-2026-MRW-001-R1) which the Owner has reviewed, approved, and accepted at a total lump-sum service fee of PHP 1,950,000.00;

NOW THEREFORE, in consideration of the mutual covenants herein, the parties agree as follows:

Article I
Scope of Services
Article I — Contractor’s Scope of Services
1.1
The Contractor agrees to provide all skilled labor, general labor, supervision, project management, and worker logistics necessary to construct the Happi Brew Main Two-Storey Building, using materials supplied by the Owner, in accordance with the approved architectural and structural plans referenced in this Contract.
1.2
Labor Scope Includes: Site preparation and earthworks (labor only); concrete works — forming, reinforcing, pouring, and curing; masonry (CHB laying — exterior 168 sqm, interior 70 sqm); plastering (476 sqm); roofing sheet installation and metal works; doors and windows installation; tile setting (floor and wall); ceiling works; painting; PEC 2017-compliant electrical rough-in, wiring, and fixture installation; National Plumbing Code-compliant plumbing rough-in and fixture installation; and final commissioning, punchlist correction, and project turnover preparation.
1.3
Management Scope Includes: One (1) Licensed Project Engineer on-site for the full construction duration; one (1) qualified Site Foreman; monthly written progress reports; quality inspection logs; coordination of worker mobilization and demobilization; and preparation of as-built documentation upon project completion.
1.4
Logistics Scope Includes: Worker transportation between Cagayan de Oro (CDO) and Marawi City (estimated 20 round trips at ₱3,500 per trip); and worker accommodation in Marawi City for a duration of five (5) months (₱28,000/month).
1.5
Exclusions from Contractor’s Scope: All construction materials (cement, rebar, aggregates, CHB, roofing materials, finishing materials, electrical materials, plumbing materials); construction equipment and power tools; scaffolding materials (unless included in the approved labor scope breakdown); and material delivery logistics from suppliers to site.
Article II
Service Fee
Manpower & PM Services — Total Service Fee
Direct Service Cost (Labor + Logistics + PM): ₱1,598,400
Overhead, Contingencies & Misc. (OCM 12%): ₱191,808
Contractor’s Profit (10%): ₱159,840
₱1,950,000
Philippine Peso · No VAT
Lump-Sum · Labor & Management Only
2.1
The Owner agrees to pay the Contractor a total lump-sum service fee of Philippine Pesos One Million Nine Hundred Fifty Thousand and 00/100 (PHP 1,950,000.00) for the complete labor and project management services described herein. No Value Added Tax (VAT) is applied per the parties’ agreement.
2.2
This service fee is fixed and covers all labor costs, management fees, worker transportation, and worker accommodation as itemized in the companion Manpower Proposal (Ref: JMG-MPS-2026-MRW-001-R1). Materials, equipment, and tools are explicitly excluded and remain the Owner’s responsibility.
2.3
Service fee adjustments may be negotiated if the approved labor scope is materially changed by the Owner, or if material delays caused by the Owner’s supply chain necessitate prolonged worker standby beyond what is absorbed in the lump-sum. Any adjustment requires a written Change Order signed by both parties.
Article III
Payment Schedule
3.1
Payment shall be released in five (5) tranches tied to labor deployment milestones as follows:
TrancheMilestone Trigger%Amount (PHP)
1stMobilization — upon contract execution, NTP, and site readiness confirmation20%390,000.00
2ndFoundation Phase Complete — footings, grade beams, ground floor slab done25%487,500.00
3rdStructural Frame — all columns, beams, second floor slab, roofing structure done25%487,500.00
4thEnclosed + MEP Rough-In — masonry, roofing, electrical & plumbing rough-in complete20%390,000.00
5thTurnover — all finishes complete, punchlist cleared, as-built documents submitted10%195,000.00
TOTAL SERVICE FEE100%₱1,950,000.00
3.2
Payment shall be released within five (5) banking days of the Contractor’s written milestone certification accompanied by progress photographs. Delays beyond fifteen (15) calendar days may result in a work suspension as provided in Article VI of this Contract.
3.3
Milestone certifications reflect the completion of labor activities only. If a milestone is delayed due to material shortages on the Owner’s part, the Contractor may certify partial completion of labor work completed to date, and the Owner shall release a proportionate partial payment as negotiated in good faith.
Articles IV, V & VI
Time of Completion, Obligations & Material Responsibility
Article IV — Time of Completion
4.1
The Contractor shall mobilize within seven (7) to ten (10) calendar days of receiving both the written NTP and the 20% mobilization payment (₱390,000.00). Proposed NTP: September 1, 2026. Target completion: January 16, 2027 (approximately 20 weeks), subject to timely material supply by the Owner.
4.2
The project schedule (Ref: JMG-SCH-OPB-2026-MRW-001) is predicated on continuous material availability on site. Any delay in material delivery that causes workers to be idle for more than two (2) consecutive working days will extend the schedule by an equivalent period. Idle days beyond five (5) consecutive days may entitle the Contractor to a standby fee not exceeding the daily payroll cost of affected workers.
Article V — Contractor’s Obligations
5.1
Quality of Work: All labor shall be performed in a professional and workmanlike manner per NSCP 2015, PEC 2017, National Plumbing Code, and DPWH specifications — regardless of whether materials are supplied by the Owner or JMG.
5.2
Material Inspection: The Contractor’s Project Engineer shall inspect all materials upon delivery and document any non-conformance in writing. The Contractor shall not install materials flagged as non-compliant until the Owner addresses the deficiency. The Contractor bears no liability for defects arising from substandard materials supplied by the Owner.
5.3
Worker Safety & Conduct: JMG is responsible for worker PPE, labor law compliance (DOLE), and site safety protocols for all JMG-deployed workers. The Owner is responsible for site perimeter security and overall site safety conditions.
5.4
Defect Liability: JMG warrants all workmanship for one (1) year from turnover. This warranty covers installation-related defects only. It explicitly excludes defects caused by substandard materials, Owner modifications, or normal wear and tear.
Article VI — Owner’s Critical Obligations
6.1
Timely Material Supply: The Owner shall ensure all required materials are on site and ready for installation at least 48 hours before each activity phase begins, per the agreed program of works. Failure to supply materials on time is a breach of the Owner’s obligation and absolves JMG of schedule accountability for the corresponding delay.
6.2
Temporary Power, Water & Equipment: The Owner shall provide and maintain temporary electricity, water supply, and any construction equipment listed in the approved scope. JMG workers cannot proceed without access to these utilities.
6.3
Permits & Access: The Owner shall secure all building permits and government clearances prior to NTP. The Owner shall ensure clear, legal site access throughout the project duration.
6.4
Timely Payments: Milestone payments shall be released within five (5) banking days of certification. Delays beyond fifteen (15) calendar days entitle the Contractor to suspend work without penalty until payment is received.
Articles VII–X
Change Orders, Force Majeure, Termination & Disputes
Article VII — Change Orders
7.1
Any change to the labor scope requires a written Change Order signed by both parties before work begins. The Contractor will provide a cost estimate within five (5) business days. Changes shall be priced at the same DPWH 2024 labor rate basis plus applicable OCM and profit.
Article VIII — Force Majeure
8.1
Neither party shall be in default for delays caused by events beyond reasonable control (natural disasters, civil unrest, government lockdowns, declared calamity). Affected party shall notify in writing within five (5) business days. Resulting schedule extensions shall be negotiated in good faith.
Article IX — Termination
9.1
Either party may terminate this Contract with fourteen (14) calendar days written notice for material breach that remains uncured ten (10) days after written notice of the breach. Upon termination, the Contractor shall be compensated for all labor services rendered to date plus reasonable demobilization costs. The Owner shall not use incomplete work without paying for all services completed.
Article X — Dispute Resolution & Governing Law
10.1
Disputes shall first be resolved through direct negotiation within fifteen (15) calendar days of written notice. If unresolved, parties may submit to mediation or the appropriate Philippine court of jurisdiction. This Contract is governed by the laws of the Republic of the Philippines.
Execution
Contract Execution

IN WITNESS WHEREOF, the parties have executed this Manpower & PM Services Contract as of the date first written above. Each party confirms having read and understood the full terms and conditions herein, including the clear division of material responsibility.

Amil Alonto & RJ Alonto
Owner — Happi Brew Main
Marawi City, Lanao del Sur
Date:
JMG Design & Build
JMG Construction & General Merchandise
Authorized Representative
Date:

Signed in the Presence of the Following Witnesses

Printed Name & Signature
Printed Name & Signature
Contract No. JMG-CON-OPB-2026-MRW-001 | MPS Ref: JMG-MPS-2026-MRW-001-R1 | BOQ Ref: JMG-2026-MRW-001-R3
Option B — Manpower & PM Services Only | Service Fee: ₱1,950,000.00 (No VAT) | August 17, 2026
Option B — Manpower & PM Services Only
Manpower Deployment Schedule

Happi Brew Main — Labor Deployment Schedule

20-Week Program of Works | September 2026 – January 2027

JMG-SCH-OPB-2026-MRW-001
September 1, 2026
January 16, 2027
20 Weeks
Amil Alonto & RJ Alonto
Happi Brew Main, Marawi City
₱1,950,000.00
JMG-CON-OPB-2026-MRW-001
Option B — Manpower & PM Services
20 Weeks · Sept 1, 2026 → Jan 16, 2027
₱1,950,000.00 · Labor & PM Only
⚠️ Important: This schedule assumes continuous, on-time material availability by the Owner. Rows marked OWNER MATERIAL indicate Owner must have these materials on-site before JMG can proceed. Delays in material supply directly delay labor deployment and extend the schedule.
Legend:
Phase 1 — Mobilization
Phase 2 — Foundation & GF
Phase 3 — 2F Structure
Phase 4 — Enclosure & MEP
Phase 5 — Finishes
Owner supplies material
 Payment Milestone
ActivitySeptember 2026October 2026November 2026December 2026January 2027
Week →W1W2W3W4W5W6W7W8W9W10W11W12W13W14W15W16W17W18W19W20
Date →1–58–1215–1922–2629–36–1013–1720–2427–313–710–1417–2124–281–58–1215–1922–2629–25–912–16
PHASE 1 — MOBILIZATION & SITE PREPARATION (Weeks 1–2)
Owner: Site cleared, access confirmed, water & power ready OWNER PRE-REQ
1.1JMG Mobilization — Team deployment from CDO to Marawi
1.2Site Clearing, Grubbing & Layout Survey
1.3Earthworks — Excavation, Embankment Fill (175 cu.m) & Compaction
💰 PAYMENT 1 — 20% Mobilization (₱390,000)
PHASE 2 — FOUNDATION & GROUND FLOOR STRUCTURE (Weeks 3–9) — Owner supplies: cement, rebar, aggregates, formwork ply
Owner: Cement, rebar, aggregate, sand on site OWNER MATERIAL
2.1Footing Excavation, Layout & Rebar Assembly
2.2Footing Concrete Pouring & Curing
2.3Grade Beams, GF Columns Rebar, Formwork & Concrete
2.4GF Beam & Slab Formwork, Rebar, Concrete Pour
💰 PAYMENT 2 — 25% Foundation Complete (₱487,500)
PHASE 3 — SECOND FLOOR STRUCTURE & ROOFING (Weeks 9–14) — Owner supplies: rebar, cement, structural steel, roofing materials
Owner: 2F rebar, structural steel, roofing sheets, purlins on site OWNER MATERIAL
3.12nd Floor Columns — Rebar, Formwork & Concrete
3.22nd Floor Beams, Slab Formwork, Rebar & Concrete
3.3Roofing Structure — Steel Purlin Setting & Roofing Sheet Installation
💰 PAYMENT 3 — 25% Structural Frame Complete (₱487,500)
PHASE 4 — ENCLOSURE, MASONRY & MEP ROUGH-IN (Weeks 12–17) — Owner supplies: CHB, cement, electrical & plumbing materials, doors, windows
Owner: CHB blocks, mortar, electrical materials, plumbing materials on site OWNER MATERIAL
4.1CHB Masonry — Ground & 2nd Floor Walls (238 sqm total)
4.2Doors & Windows — Frame Installation & Hardware
4.3Electrical Rough-In — Conduit, Boxes, Wiring, Panel (PEC 2017)
4.4Plumbing Rough-In — Supply, Drain & Vent Lines
4.5Cement Plastering — Interior & Exterior (476 sqm)
💰 PAYMENT 4 — 20% Enclosed + MEP (₱390,000)
PHASE 5 — FINISHES, MEP COMPLETION & TURNOVER (Weeks 17–20) — Owner supplies: tiles, paint, electrical fixtures, plumbing fixtures
Owner: Tiles, paint, ceiling boards, fixtures, plumbing fittings on site OWNER MATERIAL
5.1Floor & Wall Tile Setting — All Areas
5.2Ceiling Works — Framing & Board Installation
5.3Interior & Exterior Painting — Primer + Finish
5.4Electrical Fixtures, Panel, Outlets & System Testing
5.5Plumbing Fixtures, CR Works & Pressure Testing
5.6Final Inspection, Punchlist & As-Built Documentation
💰 PAYMENT 5 — 10% Turnover (₱195,000)
Deployment Summary
Phase Overview, Payments & Material Requirements
Phase 1
Mobilization & Site Prep
Weeks 1–3 | Sep 1–19
💰 20% — ₱390,000
Owner: Site access, utilities ready
Phase 2
Foundation & Ground Floor
Weeks 3–10 | Sep–Oct
💰 25% — ₱487,500
Owner: Cement, rebar, aggregates
Phase 3
2F Structure & Roofing
Weeks 9–14 | Oct–Nov
💰 25% — ₱487,500
Owner: 2F rebar, steel, roofing
Phase 4
Enclosure & MEP
Weeks 12–18 | Nov–Jan
💰 20% — ₱390,000
Owner: CHB, electrical, plumbing
Phase 5
Finishes & Turnover
Weeks 17–20 | Jan 2027
💰 10% — ₱195,000
Owner: Tiles, paint, fixtures
Total Labor Deployment
20 Weeks · September 1, 2026 → January 16, 2027
Schedule based on continuous material availability. Delays in material supply extend the program.
Total Service Fee
₱1,950,000.00
No VAT | Lump-Sum | Labor & PM Only

JMG Design & Build · Marawi City

Concept Design & Working Drawings

Proposed Two-Storey Coffee Shop Building — Happi Brew Main
Owner: A. RJ Alonto · Marawi City · All drawings at scale 1:100 unless noted

Happi Brew Main two-storey coffee shop front facade exterior concept design, Marawi City, JMG Design & Build

Click to zoom

Concept Design

Front Facade — Exterior Concept

Sheet CD-01 · Concept Design · Front Facade

Happi Brew Main ground floor dining area interior concept design view 1, Marawi City

Click to zoom

Concept Design

Ground Floor Dining Area — Interior View 1

Sheet CD-02 · Concept Design · Ground Floor Dining (View 1)

Happi Brew Main ground floor dining area interior concept design view 2, Marawi City

Click to zoom

Concept Design

Ground Floor Dining Area — Interior View 2

Sheet CD-03 · Concept Design · Ground Floor Dining (View 2)

Happi Brew Main second floor indoor dining interior concept design view 1, Marawi City

Click to zoom

Concept Design

Second Floor Indoor Dining — Interior View 1

Sheet CD-04 · Concept Design · 2F Indoor Dining (View 1)

Happi Brew Main second floor indoor dining interior concept design view 2, Marawi City

Click to zoom

Concept Design

Second Floor Indoor Dining — Interior View 2

Sheet CD-05 · Concept Design · 2F Indoor Dining (View 2)

Happi Brew Main second floor alfresco outdoor terrace concept design, Marawi City

Click to zoom

Concept Design

Second Floor Alfresco Terrace — Outdoor Dining

Sheet CD-06 · Concept Design · 2F Alfresco Terrace

Happi Brew Main service and vertical circulation stair area concept design, Marawi City

Click to zoom

Concept Design

Service & Vertical Circulation — Stair Area

Sheet CD-07 · Concept Design · Stair & Circulation

Sheet A-1 ground floor and second floor plan architectural working drawing, Happi Brew Main Marawi City

Click to zoom

Architectural

Sheet A-1 — Ground Floor & Second Floor Plans

Sheet A-1 · Architectural · Floor Plans · Scale 1:100

Sheet A-2 front rear and side elevations architectural working drawing, Happi Brew Main Marawi City

Click to zoom

Architectural

Sheet A-2 — All Four Elevations

Sheet A-2 · Architectural · Elevations · Scale 1:100

Sheet A-3 cross section longitudinal section and roof plan architectural working drawing, Happi Brew Main

Click to zoom

Architectural

Sheet A-3 — Sections & Roof Plan

Sheet A-3 · Architectural · Sections & Roof Plan · Scale 1:100

Sheet A-4 door window schedule and reflected ceiling plan architectural working drawing, Happi Brew Main

Click to zoom

Architectural

Sheet A-4 — Doors, Windows & Ceiling Plans

Sheet A-4 · Architectural · Doors, Windows & Ceiling · Scale 1:50 / 1:100

Sheet S-1 foundation plan second floor framing and roof beam structural working drawing, Happi Brew Main

Click to zoom

Structural

Sheet S-1 — Foundation, Framing & Roof Beam Plans

Sheet S-1 · Structural · Foundation, Framing & Roof Beams · Scale 1:100

Sheet S-2 wall footing column slab and truss structural details working drawing, Happi Brew Main

Click to zoom

Structural

Sheet S-2 — Structural Details

Sheet S-2 · Structural · Footing, Column & Slab Details · NTS

Sheet S-3 typical beam detail and stair detail structural working drawing, Happi Brew Main

Click to zoom

Structural

Sheet S-3 — Beam & Stair Details

Sheet S-3 · Structural · Beam & Stair Details · NTS

Sheet E-1 lighting layout ground and second floor electrical working drawing, Happi Brew Main

Click to zoom

Electrical

Sheet E-1 — Lighting Layout (Both Floors)

Sheet E-1 · Electrical · Lighting Layout · Scale 1:100

Sheet E-2 power layout schedule of loads and single line diagram electrical working drawing, Happi Brew Main

Click to zoom

Electrical

Sheet E-2 — Power Layout & Single Line Diagram

Sheet E-2 · Electrical · Power Layout & SLD · Scale 1:100 / NTS

Sheet P-1 water line and sanitary layout plumbing working drawing, Happi Brew Main

Click to zoom

Plumbing

Sheet P-1 — Water Line & Sanitary Layout

Sheet P-1 · Plumbing · Water & Sanitary · Scale 1:100

Sheet P-2 storm drainage and septic vault details plumbing working drawing, Happi Brew Main

Click to zoom

Plumbing

Sheet P-2 — Drainage & Septic Vault

Sheet P-2 · Plumbing · Storm Drainage & Septic · Scale 1:100 / NTS

Sheet M-1 airconditioning ACCU layout mechanical working drawing, Happi Brew Main

Click to zoom

Mechanical

Sheet M-1 — Airconditioning Layout

Sheet M-1 · Mechanical · ACCU Layout · Scale 1:100

Sheet EC-1 CCTV layout and security surveillance working drawing, Happi Brew Main

Click to zoom

ELV / Security

Sheet EC-1 — CCTV Surveillance Layout

Sheet EC-1 · Extra Low Voltage · CCTV · Scale 1:100