๐Ÿ“… Planned Finish Nov 30, 2026
๐Ÿšฉ Forecast Finish Feb 02, 2027
โณ Slip +64 days
๐Ÿ“Š Progress ~44%
๐Ÿ‘ท Status Active ยท Re-org done
๐Ÿ“ˆ Gantt Chart: Master vs Actual 15 Activities
โ–ฌ Master Plan โ–ฌ On-Track Actual โ–ฌ Delayed Actual โณ Today: Aug 14, 2026
๐Ÿ“‹ Detailed BOQ (5th Billing) โ‚ฑ7.38M Total
ItemContract PriceProgressBilledRemainingStatus
๐Ÿ•’ Latest Activity Live
๐Ÿ’ก Management Notes
  • Manpower Re-org completed Jun 6. Crew stabilized.
  • Critical: Roofing & Finishes must accelerate.
  • Steel Deck delivered & staged (Jun 27).
  • Forecast: Turnover moved to Feb 2027.
โฑ๏ธ Next milestone: Complete Roofing by Sep 15.